#1, #10, #13, #14, #18, #42, #59, #80, & #95 / Central West End Construction of Walkway Bridge / Plans A, B, and C (7pm to 4am nightly)

MetroLink Alerts
MetroLink Alerts
MetroLink RSS Feed
          Stations
 
Construction
 
DETAILS
Update: Plan A will be in effect for approx. 7 weeks beginning Monday, July 25th

CENTRAL WEST END STATION CONSTRUCTION
BJC over the next few months will be installing an enclosed walkway bridge connecting parking garages on east side of Taylor Ave. to Euclid Ave. This will allow employees of BJC Complex to walk in an enclosed area from parking garages to main campus. As construction progresses different entrances and exits to bus bays at CWE Station will be closed. Metro has three different routing of buses during construction.
1. All work will start at 7:00PM
2. All work will end by 4:00AM
3. Each day Comm. Center will announce witch plan will be implemented a. Plan “A” b. Plan “B” c. Plan “C”
4. When work is preformed the contractor will post signs in and around the CWE Station to provide information to Metro customers.