Updated 11/20/2014 at 12:52 p.m.: Track maintenance this weekend (Nov. 22 and Nov. 23) is cancelled. 

Rail maintenance work on the MetroLink system may result in brief delays for some Red Line and Blue Line passengers next week, so customers are encouraged to allow a little extra time for their commutes.

To accommodate the crews, MetroLink will operate on a single track at the Wellston MetroLink Station, the Rock Road MetroLink Station, Richmond Heights MetroLink Station and the Brentwood I-64 MetroLink Station.

  • Monday through Thursday (Nov. 17-20) from 8 p.m. until the end of service each night, MetroLink will operate on a single track at the Wellston and Rock Road Stations. Red Line customers may experience 5 to 10 minute delays. The Blue Line will not be impacted by this work.
  • On Friday (Nov. 21) from 8 p.m. until the end of service, MetroLink will operate on a single track at the Richmond Heights and Brentwood I-64 Stations. Blue Line customers may experience 5 to 10 minute delays. The Red Line will not be impacted by this work.

Updates on MetroLink operations can be found online in the Rider Alert section.

Categories:
Construction

Your email address will not be published. Required fields are marked *

Contact to Listing Owner

Captcha Code