October 25, 2013

MetroLink Work Scheduled October 28 – November 3

Patti Beck
Director of Communications
314-982-1524

Work is scheduled on the MetroLink system Monday through Sunday (October 28 – November 3), and some passengers may experience short delays in the work zones. The affected areas of the MetroLink system are:

• Forest Park-DeBaliviere MetroLink Station
• Delmar Loop MetroLink Station
• Wellston MetroLink Station
• Rock Road MetroLink Station
• Maplewood Manchester MetroLink Station
• Sunnen MetroLink Station

MetroLink will operate on a single track between the Delmar Loop and Forest Park-DeBaliviere Stations Monday and Tuesday (October 28-29) to accommodate crews conducting track maintenance. On Monday, single track will occur from 11:30 p.m. until end of service, and Tuesday from 8 p.m., until the end of service. Red Line passengers may experience 5-10 minute delays. Blue Line service will not be affected.

MetroLink will operate on a single track between the Rock Road and Wellston Stations Wednesday through Friday (October 30 – November 1) and Sunday (November 3) from 8 p.m. until end of service to accommodate track maintenance work. Red Line passengers may experience 5-10 minute delays. Blue Line service will not be affected.

MetroLink will operate on a single track between the Maplewood Manchester and Sunnen Stations Tuesday through Thursday (October 29 – October 31) starting at 11:30 p.m. to accommodate crews conducting track maintenance. On Saturday and Sunday (November 2-3), single track operations will occur from 6 a.m. until 4 p.m. Blue Line passengers may experience 5-10 minute delays. Red Line service will not be affected.

Updates on MetroLink operations can be found at www.metrostlouis.org in the Rider Alert section.

The Bi-State Development Agency/Metro (BSDA/Metro) is the operator of the Metro public transportation system for the St. Louis region, which includes the 87 vehicle, 46-mile MetroLink light rail system; 378 MetroBus vehicle fleet that operates on 75 MetroBus routes; and Metro Call‑A‑Ride, a paratransit fleet of 121 vans.

BSDA/Metro also owns and operates St. Louis Downtown Airport and its surrounding industrial business park, and the Gateway Arch Riverboats, as well as operates the Gateway Arch Revenue Collections Center, the Gateway Arch Transportation System, and the Gateway Arch Parking Facility.

Contact to Listing Owner

Captcha Code